The operator of Japan's crippled Fukushima nuclear plant has paid way over the odds to contractors, a company spokesman said Friday, vowing to boost cost-controls at the taxpayer-subsidised firm.

An internal probe looking at how contracts worth 1 trillion yen ($10 billion) were awarded has found the company routinely paid a lot more than the going rate because prices were inflated by layers of subcontractors.

The revelation comes as the Japanese government readies to nearly double its financial support for the cash-stripped utility as part of efforts to speed up the removal of contamination in residential areas around the plant and to process compensation payments for victims.

The in-house panel found Tokyo Electric Power Co. (TEPCO) agreed to pay 21 million yen ($200,000) for some construction work linked to a nuclear power plant, but this work could have been done for about half that, the spokesman confirmed.

In another instance, TEPCO was paying a contractor 49,000 yen in daily wages for one worker, but it would have paid only 12,000 yen if it had employed the man directly.

"We've been making cost reduction efforts with the panel, and we will further cut costs including in areas pointed out by the panel," the spokesman said.

The ramping is the result of farming out work to contractors, who themselves sub-contract, sometimes having hired retired TEPCO officials, the Asahi Shimbun, which first reported the case, said.

The revelation will be a further embarrassment to bosses at the beleaguered firm, which has earned a reputation for inefficiency and ineptitude since the tsunami of March 2011 sent reactors at Fukushima into meltdown.

Japanese taxpayers were forced in 2012 to stump up billions of dollars to keep the giant utility afloat as it struggled with the enormous costs of decommissioning the reactors, cleaning up the mess they have made and paying compensation to people who lost their homes to the disaster.

The government last month approved a further $1 billion to pay for facilities to store radioactive waste.

Under a restructuring plan submitted at the end of last year, TEPCO said it wants to cut costs by 3.365 trillion yen between fiscal 2012 and 2021 through measures that would include a greater use of competitive bidding in procurement.

Critics say that Japan's utilities, which have near-monopolies on both the production and distribution of power, have little financial savvy because they have never faced competition and are accustomed to being able to pass on costs to consumers.

They add taxpayers repeatedly find themselves on the hook because of fears that if TEPCO went under, it could deal a huge blow to the viability of some of its lenders, which would have knock-on effects in other parts of the economy.

Its failure could also affect electricity production in the economically-vital Tokyo area.

TEPCO and Japan have yet to figure out the exact cost of compensating tens of thousands of people who had to flee their homes and livelihoods to avoid radiation.

.


Related Links
Nuclear Power News - Nuclear Science, Nuclear Technology
Powering The World in the 21st Century at Energy-Daily.com






Comment on this article via your Facebook, Yahoo, AOL, Hotmail login.

Share this article via these popular social media networks
del.icio.usdel.icio.us DiggDigg RedditReddit GoogleGoogle








CIVIL NUCLEAR
Japan scientists to create controlled nuclear meltdown
Tokyo (AFP) Jan 09, 2014
A team of nuclear scientists in Japan said Thursday they plan to create a controlled reactor meltdown in a bid to learn how to deal with future disasters like that at Fukushima. The Japan Atomic Energy Agency said it was working on a project using a scaled-down version of a reactor which they would deliberately cause to malfunction at a research facility in Ibaraki, north of Tokyo. "We w ... read more


CIVIL NUCLEAR
Israel moves closer to anti-missile shield with Arrow 3 test

Satellite of Russia's early warning constellation burns down in atmosphere

Raytheon begins building 12th AN/TPY-2 ballistic missile defense radar

SBIRS Geo-2 Missile Defense Early Warning Satellite Certified For Operation

CIVIL NUCLEAR
Israel successfully tests Arrow space missile interceptor

Israel, US carry out missile test during Kerry visit

Raytheon awarded $80.5 million from US Navy for Joint Standoff Weapon

Missiles fired from Lebanon trigger Israel shelling: army

CIVIL NUCLEAR
UAS Test Site Selection Good News for NASA Langley, Wallops

US names drone testing sites

FAA announces locations for future drone testing sites

US drone strike kills three in northwest Pakistan

CIVIL NUCLEAR
Rocket Rokot brings 3 Russian military-purpose satellites on orbit

US Air Force selects Raytheon's high-bandwidth satellite terminal for secure, protected communications

Military Communication Improved as 6th Boeing-built Wideband Satellite Enters Service

Radio Gateway Connects US and Allied Troops to a Common Mobile Network

CIVIL NUCLEAR
Raytheon awarded $12.9 million Cooperative Engagement Capability contract

Boeing Delivers Final Focused Lethality Munition to USAF

US Army Awards Raytheon contract for Excalibur Ib

Russia's Kalashnikov, designer of AK-47, dies

CIVIL NUCLEAR
Hollande drives for arms deals in Persian Gulf as U.S. power wanes

Outgoing German defence minister in parting shot at France, Britain

Aborted defence deal underlines India's procurement problem

Nexter calls for bidding expense reimbursement

CIVIL NUCLEAR
France, Japan vow to strengthen defence ties amid China spat

China calls for 'warning' to Japan over war tribute

Critical Gates memoir rocks Obama administration

Outside View: Three New Year's wishes

CIVIL NUCLEAR
Extraordinary sensors pushed to their boundaries

Understanding secondary light emissions by plasmonic nanostructures

No nano-dust danger from facade paint

Discovery at nanoscale has major implications for manufacturers




The content herein, unless otherwise known to be public domain, are Copyright 1995-2014 - Space Media Network. AFP, UPI and IANS news wire stories are copyright Agence France-Presse, United Press International and Indo-Asia News Service. ESA Portal Reports are copyright European Space Agency. All NASA sourced material is public domain. Additional copyrights may apply in whole or part to other bona fide parties. Advertising does not imply endorsement,agreement or approval of any opinions, statements or information provided by Space Media Network on any Web page published or hosted by Space Media Network. Privacy Statement