Loss of Vega flight VV17 report issued
by Staff Writers
Paris (ESA) Dec 18, 2020

Stock image of a Vega launch.

Initial investigations, conducted right after the launch with the available data, identified a problem related to the integration of the fourth-stage AVUM Thrust Vector Control (TVC) system as being the most likely cause of the loss of control of the launcher.

Arianespace (the launch service provider) and the European Space Agency (ESA - the launch system development authority) immediately set up an Independent Enquiry Commission (IEC). The Commission provided the detailed report and conclusions confirming initially identified root causes to the failure, comprehensively explaining what went wrong in the integration process and why the error was not detected before flight. According to its findings, the Commission has accordingly formulated a road map for a robust Vega return to flight.

More precisely, the IEC concludes that the VV17 cause of failure is not attributable to a flaw in the qualification of the design but to the wrong routing and connection of the control lanes of the electro-mechanical actuators of the AVUM upper stage Thrust Vector Control (TVC) system, inverting steering commands and causing trajectory degradation leading to the loss of the vehicle. The detailed series of causes are described as

(i) a misleading integration procedure causing

(ii) an inversion of electrical connections, not detected through

(iii) the different control steps and tests executed between the integration of the AVUM upper stage and the final acceptance of the launcher due to some inconsistencies between specific requirements and prescribed controls.

A comprehensive set of both immediate and permanent recommendations has been presented by the IEC to ensure safe and prompt return to flight, as well as to ensure launch vehicles reliability on the long term. The first set of recommendations include additional inspections and tests on the next two Vega launchers, whose hardware is already totally or partially produced, and workmanship.

Permanent recommendations have been proposed to further mitigate the identified root causes, regarding the manufacturing, integration and acceptance processes on Vega assembly lines in Italy and its final acceptance in French Guiana.

Starting this week, a task force steered by ESA and Arianespace has started implementing the roadmap proposed by the IEC and will thoroughly follow its implementation.

A set of actions will be implemented by Vega's prime contractor Avio, under the supervision of Arianespace, as launch service provider, and ESA, as launch system development authority, in order to make possible the next Vega launch, VV18, still scheduled by Q1 2021 from French Guiana, and the following ones.

"Thanks to their hard work in less than one month, the members of the Commission have confirmed the cause initially identified after the loss of control of the mission VV17," said Stephane Israel, CEO of Arianespace.

"The clarity of the conclusions presented by the Independent commission opens the way to immediate implementation by Avio, Vega's prime contractor, of the recommendations on their integration line, with the support from Arianespace and ESA. It may allow a return to flight by end Q1 2021, in full confidence to Vega's quality and competitiveness on the market."

Daniel Neuenschwander, ESA Director of Space Transportation, said: "In the past few weeks, members of the Independent Inquiry Commission have done an exceptional work, with the support of the prime contractor Avio. The Commission has drawn a set of recommendations that once implemented should enable robust, reliable and even swift return to flight of Vega, contributing to secure Europe's autonomy of access to space."

A comprehensive set of both immediate and permanent recommendations has been presented by the IEC to ensure safe and prompt return to flight, as well as to ensure launch vehicles reliability on the long term.

The first set of recommendations include additional inspections and tests on the next two Vega launchers, whose hardware is already totally or partially produced, and workmanship.

Permanent recommendations have been proposed to further mitigate the identified root causes, regarding the manufacturing, integration and acceptance processes on Vega assembly lines in Italy and its final acceptance in French Guiana.


Related Links
ESA Space Transportation
Rocket Science News at Space-Travel.Com

ROCKET SCIENCE
Loss of Vega flight VV17: Independent Enquiry Commission announces conclusions
Paris (ESA) Dec 18, 2020
Initial investigations, conducted right after the launch with the available data, identified a problem related to the integration of the fourth-stage AVUM Thrust Vector Control (TVC) system as being the most likely cause of the loss of control of the launcher. Arianespace (the launch service provider) and the European Space Agency (ESA - the launch system development authority) immediately set up an Independent Enquiry Commission (IEC). The Commission provided the detailed report and conclusions c ... read more

Comment using your Disqus, Facebook, Google or Twitter login.

Share this article via these popular social media networks
del.icio.usdel.icio.us DiggDigg RedditReddit GoogleGoogle

ROCKET SCIENCE
IMDO and MDA complete intercept test of the David's Sling Weapon System

Most Advanced SBIRS Missile Warning Satellite Ready For 2021 Launch

Russian military successfully tests new anti-ballistic missile

Navy intercepts, destroys ICBM during missile test in Hawaii

ROCKET SCIENCE
AFRL demonstrates critical new warhead technologies for high speed weapons

Projectile concept shows potential to extend munition range to more than 100km

U.S., Australia agree to partner on hypersonic missile development

Tigray forces fire rockets at Ethiopian regional capital

ROCKET SCIENCE
German government at odds over armed drones

Funding for MQ-9 Reaper drone back in federal budget

Northrop Grumman completes first flight of Global Hawk Ground Station Modernization Program

Air Force launches drone-based security system at Travis AFB

ROCKET SCIENCE
NATO checking systems after US cyberattack

L3Harris to build Next Generation jammers in $496 million contract

DARPA successfully demonstrates, transitions advanced RF networking program

DARPA successfully demonstrates, transitions advanced RF networking program

ROCKET SCIENCE
U.S. Marines begin rollout of small-arms suppressors

Tyndall AFB in Florida conducts Weapon System Evaluation Program

General Dynamics to build upgraded Abrams tanks in $4.62B contract

GM Defense begins renovating N.C. facility to build ISVs

ROCKET SCIENCE
State Dept. approves $300M bomb sale to Saudi Arabia

The Bavarian town where US troops are life and soul

State Department approves possible $4.2B in weapons sales to Kuwait

Trump vetoes sweeping US defense bill

ROCKET SCIENCE
U.S. warships travel Taiwan Strait; China warns against show of force

Russia, Turkey to develop military ties despite US sanctions

Turkey will lead NATO's high-readiness force in 2021

NATO intercepted hundreds of Russian planes over Europe in 2020

ROCKET SCIENCE
Atomic-scale nanowires can now be produced at scale

Weak force has strong impact on nanosheets

Making 3D nanosuperconductors with DNA

Researchers share design for affordable single-molecule microscope