New one year delay at UK Hinkley Point nuclear plant: EDF
Paris, May 19 (AFP) May 19, 2022
An already-delayed giant nuclear plant in southwest England will open a year later than planned and cost up to pound3 billion more than previously thought, French electricity giant EDF said Thursday.

The total cost of Hinkley Point C, which aims to provide seven percent of Britain's total power needs, had already swelled to as much as pound23 billion and had been due to begin generation in June 2026, already well behind schedule.

Hinkley Point is Britain's first new nuclear power plant in more than two decades.

"The start of electricity generation for Unit 1 is targeted for June 2027, the risk of further delay of the two units is assessed at 15 months, assuming the absence of a new pandemic wave and no additional effects of the war in Ukraine," EDF said in a statement adding that costs were now estimated between pound25 billion ($31 billion, 30 billion euros) and pound26 billion.

EDF said in its statement that there would be no additional cost to British consumers.

"During more than two years of the Covid-19 pandemic, the project continued without stopping. This protected the integrity of the supply chain and allowed the completion of major milestones. However, people, resources and supply chain have been severely constrained and their efficiency has been restricted.

"In addition, the quantities of materials and engineering as well as the cost of such activities, including, in particular marine works have risen," it added.


- 'Risky and expensive' -


Britain has a total of 15 nuclear reactors at eight sites around the country, but many of them are now approaching the end of their lifespan.

However, the government wants to maintain the 20 percent of electricity it generates from nuclear to help meet its pledge to reduce carbon emissions to net zero by 2050 and tackle climate change.

Critics have focused on the proposed design, which uses a new European Pressurised Reactor (EPR) system that has been beset by huge cost overruns and delays at sites in France and Finland.

Britain's National Audit Office has long criticised the scheme, with the watchdog saying the government has "locked consumers into a risky and expensive project with uncertain strategic and economic benefits".

Launched in 1992 as the pinnacle of French nuclear technology, the EPR was originally developed by Areva in a joint venture with Germany's Siemens, which later withdrew.

Later taken over by EDF, the project called for a plant able to operate for 60 years using pressurised water technology, the most widely-used in reactors around the world.

Similar problems to those at Hinkley have hit EDF's project at Flamanville in western France, although the firm has successfully launched two reactors with Chinese partners in Taishan, China.


ADVERTISEMENT




Space News from SpaceDaily.com
Russian space chief to meet NASA head for first time in eight years
BlackSky to supply satellite imagery and analytics for Latin American security operations
Cascade raises 59M to develop full stack satellite communications platform

24/7 Energy News Coverage
Palantir, the AI giant that preaches US dominance
China and US wrap first day of trade talks
'Food on table' outweighs health risks for Philippine e-waste dismantlers

Military Space News, Nuclear Weapons, Missile Defense
North Korea warns US against pushing it to give up nukes
Iran vows stronger response if attacked again by US, Israel
Ukraine says Russian attacks targeted western city, home to airfield

24/7 News Coverage
BAE Systems completes delivery of NOAA and NASA space weather satellites for fall launch
Building blocks of life found in distant star system suggest origins in interstellar space
Deep-sea fish confirmed as a significant source of ocean carbonate



All rights reserved. Copyright Agence France-Presse. Sections of the information displayed on this page (dispatches, photographs, logos) are protected by intellectual property rights owned by Agence France-Presse. As a consequence, you may not copy, reproduce, modify, transmit, publish, display or in any way commercially exploit any of the content of this section without the prior written consent of Agence France-Presse.