How to decommission a nuclear power plant
Frankfurt, Germany, April 15 (AFP) Apr 15, 2023
Germany's last three nuclear power plants will stop generating electricity from Saturday but the arduous and decades-long process of decommissioning the sites is only just beginning.

Here's a look at what happens after the plants are taken offline.


- Gradual shutdown -


On the day of the shutdown, plant operators will gradually decrease electricity output.

From 10:00 pm (2000 GMT), "we will lower the facility's power output by 10 megawatts per minute", Carsten Mueller, plant manager for the Isar 2 site near Munich, told the Bild newspaper.

When the reactor's power level drops to around 30 percent, "no more electricity will be fed into the high-voltage network and the generator will be automatically disconnected from the power grid", he said.

A similar process will take place in the turbines of the Emsland plant in northwest Germany and at Neckarwestheim in the southwest.

The Neckarwestheim plant has already been running "at about 70-percent capacity" since mid-January, said Joerg Michels, head of the nuclear power division at energy company EnBW, which operates the site.

Bringing a nuclear plant to a halt is actually a "routine process" often used during inspections, Michels said.

"What's unusual now is that it will happen for the last time."

Once the nuclear reactor is rendered less powerful, it will no longer send hot, pressurised water to the machine room, where the turbines will subsequently stop producing electricity.

Although no ceremonies are planned at Neckarwestheim to mark the occasion, management will be on site "out of respect" for the roughly 650 remaining employees, Michels said.


- Cooling and dismantling -


Over the following days, the atomic chain reaction sustained by the nuclear fuel rods will be "completely stopped" to allow for the "cooling of the plant's nuclear cycle", Michels said.

As part of its exit from nuclear energy, Germany has opted for the immediate dismantling of the plants once they have been disconnected from the grid, rather than mothballing the facilities.

At Neckarwestheim, the 193 fuel elements in the reactor's core -- which are still highly radioactive -- will be transferred to a water-filled pool in an adjacent building.

The fuel elements will remain immersed for three to five years until they are packed into special "Castor" casks for interim storage.

The dismantling of each component of the power plant will start "at the beginning of next year", once all the permits have been obtained, Michels said.

"We are well prepared," he added, given that EnBW already has four other reactors undergoing dismantling.

The dismantling of Germany's last three nuclear installations is expected to take around 15 years.


- Final resting place -


Germany plans to bury its highly radioactive waste deep in the ground.

But the decision on where exactly this last resting place should be is taking longer than planned, with suggested locations often running into opposition from nearby residents who fear health hazards.

A choice on the final repository was initially due by 2031, with the aim of having the site operational by 2050.

But late last year the German body in charge of nuclear waste disposal said a suitable location would likely be found only between 2046 and 2068.

Once the site has been identified, the planning, licensing and construction of the repository is expected to take around two decades.

The final repository eventually selected must be able to safely store radioactive waste for a million years.

In the meantime, the highly radioactive waste will be held in specially designed interim storage facilities.

For medium- and low-level radioactive waste, a permanent repository has already been found at the former Konrad iron ore mine near Salzgitter in central Germany. The site is set to become operational in 2027.

"More than 30,000 generations will still be affected by the consequences of nuclear power technology, which has only been used in our country for 60 years," former environment minister Barbara Hendricks said in 2017.


ADVERTISEMENT




Space News from SpaceDaily.com
AI systems proposed to boost launch cadence reliability and traffic management
China debuts Long March 12A reusable rocket in Jiuquan test flight
Curiosity Blog, Sols 4750-4762: See You on the Other Side of the Sun

24/7 Energy News Coverage
Redesigned carbon framework boosts battery safety and power
Molecular catalyst switches between hydrogen and oxygen production
Project Pele microreactor reaches key milestone with first TRISO fuel delivery

Military Space News, Nuclear Weapons, Missile Defense
SDA expands Tracking Layer satellite awards and related missile defense contracts
Space Systems Command activates System Delta 80 for assured space access
Rheinmetall ICEYE Space Solutions to provide SAR reconnaissance data to German military

24/7 News Coverage
OPERA satellite data sharpens US crop and water management
Alen Space begins SATMAR satellite validation over Bay of Algeciras
Deep Arctic gas hydrate mounds host ultra deep cold seep ecosystem



All rights reserved. Copyright Agence France-Presse. Sections of the information displayed on this page (dispatches, photographs, logos) are protected by intellectual property rights owned by Agence France-Presse. As a consequence, you may not copy, reproduce, modify, transmit, publish, display or in any way commercially exploit any of the content of this section without the prior written consent of Agence France-Presse.